Craft Furniture Pro - production of cabinet furniture
The furniture manufacturer worked with individual orders: measurement, design, specification, material procurement, production, delivery, installation and reclamation, and had to link sales, shop, supply and assembly teams into one controlled stream.
The starting point
Managers promised customers deadlines, but they didn't always see the workload and the materials, and the production received specifications in different versions, and the installation learned about the transfers after the client had clarified.
The manager saw the problem as a fact: the client asked for status, the material didn't show up, the shop was overloaded or the crew wasn't ready to be installed.
What had to be decided
- Link the application, measurement, specification, materials, production, delivery and installation.
- Make visible the loading of the workshop and installation crews.
- Remove discrepancies in specifications and client changes.
- Give the manager a list of orders with the risk of postponement.
What did you do?
Described the order path
We have spread the order into stages from the first appeal to installation, closing of documents and possible complaints.
Collected Business OS cards
The order card appeared the client, measurement, specification, materials, production dates, installation, responsible and documents.
Set up change control
Changes in the specification were recorded as separate events with the owner, the timing and the impact on the date of installation.
Started planning.
The head sees the workload of the shop, the order queue, materials at risk and the calendar of installation teams.
Results
What's changed at work?
- The number of installation transfers decreased by 29%.
- Orders without a relevant next step were down 22 percent.
- Managers stopped promising dates without checking production and materials.
- The executive began to see the risks on orders before the customer called.
What the chief now sees
- Orders for statuses and responsible.
- Loading of the workshop and installation crews.
- Materials, changes in specifications and transfer risks.
- Closing and closing of documents for each order.